Veteran Robbins TBM Plays a Main Role in Ending Residential Flooding

Chicago’s Albany Park Diversion Tunnel to go online this spring  

In Chicago, Illinois, USA Kenny Construction is nearing completion on the Albany Park Stormwater Diversion Tunnel. The project, owned by the Chicago Department of Transportation, will divert water from the Albany Park neighborhood, which has long been plagued by flooding. Plans for the tunnel began in 2013, after flood conditions became so severe that residents had to be evacuated from the area by boat. The tunnel is expected to be functional by April 2018.

A Robbins Main Beam Hard Rock TBM bored the tunnel and broke through at the end of August 2017, bringing the project one step closer to completion. The TBM, also known as “Keri,” has been owned by project contractor Kenny Construction since the 1990s and has been used on several projects prior. “The machine holed through into the inlet shaft,” said Clay Spellman, Project Manager for Kenny Construction. “We excavated the shaft as part of the project. The machine has since been disassembled and removed.”

For the Albany Park Project, Keri was rebuilt by Kenny Construction with size modifications designed by Robbins. Robbins took an existing cutterhead, repaired it, and then added segments, taking it from 5.2 m (17.2 ft) to 6.2 m (20.4 ft) in diameter. “Extensive modifications were also made underground to the machine to be able to install rock dowels and stand the ring steel under the roof shield,” added Spellman.

“Rebuilding TBMs has always been a core part of Robbins’ business. Most customers immediately recognize that a rebuilt machine with updated systems can offer exceptional value without increasing risk, and a rebuilt machine can usually be delivered faster,” said Robbins Engineering Manager Steve Smading. “While the financial and schedule advantages are obvious, the flexibility of used equipment may be less obvious. Boring diameters can be increased or decreased and machine configurations can even be changed. For example, a Single Shield can be reconfigured as a Double Shield or vice versa, and a Main Beam TBM can be reconfigured as a shielded machine. Soft ground machines can be configured for different geologies and can be set up as either Slurry or EPB.”

Over 50 percent of all Robbins Main Beams ever manufactured have been used on three or more projects. Incredibly, many Robbins TBMs that have been used on multiple projects are approaching over 50 km (31 mi) of use. Prior to its ownership by Kenny, Keri has successfully bored tunnels in the Dominican Republic, Saudi Arabia, New York, and Chicago—totaling at least 19.5 km (12 mi) of tunnel.

Due to the project location in a residential neighborhood, there were restrictions in place as to when the machine could operate and the frequency at which blasting would be allowed per day. Despite these limitations, the TBM achieved a best day of 39.5 m (129.7 ft) and a best week (5 days) of 146.4 m (480.4 ft). The machine bored through dolomite with an average compressive strength of 64 MPa UCS (9,300 psi). “During boring we encountered approximately 30.4 m (100 ft) of fractured ground that had to be supported with rolled channels, straps, and 19 full circle steel rings,” said Spellman.

The drainage tunnel starts in Eugene Park and extends for approximately one mile under Foster Avenue to the North Shore Channel. When the Chicago River’s water levels reach flood stages—exceeding 2 m (7 ft)—the tunnel will divert a flow of 65 cubic meters (2,300 cubic ft) of water per second, avoiding Albany Park, then deposit it into the Channel. The tunnel will essentially be transferring the water where it would have ended up, without damaging the residential area or adversely affecting the river’s wildlife.

Image 1: The 6.2 m (20.4 ft) diameter Robbins Main Beam TBM broke through in August 2017 on Chicago, USA’s Albany Park Diversion Tunnel, which will go online this April.
Image 2: The resilient machine was rebuilt by Kenny Construction with size modifications designed by Robbins.

Morty the Sewer Rat Travels with Michael Bryne Manufacturing on 84″ Auger

Mortimer the Sewer Rat and now his protege, Morty Jr., have been busy traveling around the country raising the awareness for trenchless technology! This year Morty traveled with Iowa Trenchless and with Michael Bryne Manufacturing.

Just yesterday, Morty and Jim Weist, CEO and President of Michael Bryne Manufacturing, headed south in the snow with an 84″ diameter auger and cutting head for a project!

Iowa Trenchless and Michael Bryne Manufacturing generously sponsored Morty this past year by winning him during NASTT’s 2017 Educational Fund Auction. Interested in sponsoring Morty for 2018?

Join us at the auction in Palm Springs, Monday, March 26!

 

GSSI Proudly Announce Launch of New Website

GSSI, the world’s leading manufacturer of ground penetrating radar (GPR) equipment, has launched its dynamic new website. With a completely redesigned look and feel that makes it easier than ever to use, the website’s homepage is designed to help customers explore GSSI’s product range. It features a helpful and easy to use product configurator, quick access to the training class calendar, and all the latest news and updates, including the most recent case studies and videos.

The new Innovation Lab section spotlights GSSI’s most recent engineering initiatives and custom solutions. Learn about GSSI’s approach to developing customer solutions and examples of successful processes used to meet customers’ challenges.

The product pages feature a wealth of pictures showing the equipment in action and clear explanations of applications for which it is most useful. Users will also find data examples for each application and product, detailed product specifications, and a host of support material to help users get the most out of the equipment.

The expanded training section – now called GSSI Academy – includes an enhanced class schedule, trainer bios, training request form, and easy to understand explanations about GPR and electromagnetic induction (EM) technology.

The new website also features a greatly expanded support page, which now includes direct access to user manuals and software updates.

For more information on GSSI and to see the new website in action, visit www.geophysical.com.

About GSSI

Geophysical Survey Systems, Inc. is the world leader in the development, manufacture, and sale of ground penetrating radar (GPR) equipment, primarily for the concrete inspection, utility mapping and locating, road and bridge deck evaluation, geophysics, and archaeology markets. Our equipment is used all over the world to explore the subsurface of the earth and to inspect infrastructure systems non-destructively. GSSI created the first commercial GPR system over 45 years ago and continues to provide the widest range and highest quality GPR equipment available today.

NASTT’s Hall of Fame

Did you know that in 2010, the NASTT Board of Directors voted to create a Hall of Fame in order to ensure that the Society’s most outstanding and praiseworthy members received due recognition? It’s true!

The intent of the NASTT Hall of Fame is to preserve the outstanding accomplishments of exceptional individuals and to honor their contributions to the advancement of both the trenchless industry and the Society. Members may be elected from all five NASTT membership categories: Manufacturers and Suppliers; Engineers and Consultants; Municipal and Utility Employees; Contractors; and Academia.

Congratulations to this year’s inductees:
Chris Brahler
Ian Doherty
George Ragula

NASTT’s Hall of Fame award will be presented each year at NASTT’s No-Dig Show during the Gala Awards Dinner. We hope you will join us to celebrate the induction!

Click here to view all of the Hall of Fame Classes!

Click here to view the qualifications, nominations and election process information and to nominate someone for the 2019 class.

 

Robbins Main Beam Breaks Records in China

Challenging Ground Conditions are No Match for Talented Team and their TBM

 In Jilin, one of the three provinces of Northeast China, a 7.9 m (26 ft) diameter Robbins Hard Rock Main Beam TBM has achieved a national record for 7 to 8 meter (23 to 26 ft) machines: 1,423.5 m (4,670 ft) in one month. The record tops a previously-set achievement on the same project from earlier in 2017, when the TBM advanced at a rate of 1,336.8 m (4,386 ft) in one month.

The world record for the size class is held by another Robbins machine, set more than 20 years ago at the Tunnel and Reservoir Plan (TARP) in Chicago, Illinois, USA, for 1,482 m (4,862 ft) in one month. However, given the differences in rock conditions this Jilin project record is very significant. At TARP the rock was relatively homogeneous dolomitic limestone averaging 145 MPa/21,100 psi with occasional rock bolts; at Jilin the rock types were rated from 35 to 206 MPa UCS (5,100 to 30,000 psi), and identified as tuff, granite, sandstone, and andesite with multiple fault zones—conditions requiring nearly continuous ground support.

Despite the difficult conditions, the Jilin machine has achieved an average monthly advance rate of 708.3 m since the start of boring in March 2015—more than three times the average monthly rate of a Drill & Blast operation on another section of the project. “It is now very evident that well-equipped, open-type Main Beam TBMs with specialized features for difficult ground can traverse faults and large water inflows much faster than conventional tunneling methods. This fact, coupled with the high performance capabilities as demonstrated at Jilin, lowers the cost and time to complete long tunnels in difficult ground,” said Robbins President Lok Home.

The Jilin Lot 3 tunnel, which is being bored as part of a water conservation project, will be 24.3 km (15 mi) long when complete. Under contractor Beijing Vibroflotation Engineering Co. Ltd. (BVEC), the machine has excavated 14 km (8.7 mi) of the tunnel as of January 2018.

Throughout its bore, the Main Beam is expected to traverse a total of 24 fault zones. The TBM was designed accordingly, and is equipped with four rock drills, McNally pockets in the roof shield for the ability to install McNally slats, a ring beam erector, and a shotcrete system.  The McNally slats were used in difficult ground encountered in the tunnel.

The McNally Roof Support System was designed and patented by C&M McNally and licensed for exclusive use on Robbins TBMs in certain markets. By replacing the roof shield fingers on a Main Beam TBM, the McNally system prevents movement of loose rock in the critical area immediately behind the cutterhead support. The system has been tested and proven on projects worldwide—including the world’s second deepest civil works tunnel, the 2,000 m (1.2 mi) deep Olmos Trans-Andean Tunnel in Peru—to increase advance rates while still maintaining worker safety on Main Beam machines in difficult rock conditions.

The Jilin TBM’s first fault zone was encountered after just 87 m (285 ft) of boring, requiring cooperation between the owner, Jilin Province Water Investment Group Co., Ltd., contractor BVEC, and Robbins field service. Water inflows and collapsing ground in a section measuring 1,196 m (3,926 ft) long were resolved with a combination of McNally slats, grouting, and consolidation of the ground ahead of the machine. Ground support overall consists of wire mesh and shotcrete. Tunnel Reflection Tomography (TRT)—a method of ground prediction using seismic waves—is also being used to detect changing conditions ahead of the TBM.

Despite the initial challenges, the TBM is now achieving between 40 and 60 m (130 to 197 ft) advance per day. “My colleagues and I all feel that the Robbins TBM is very easy to operate.  All components of the system work well during operation, which has ensured our good progress,” said by Tao Yong, BVEC Jilin Lot 3 TBM Site Manager.

The Jilin Lot 3 tunnel is part of the Jilin Yinsong Water Supply Project, which will convey water to the central cities of Jilin Province.  The large-scale, trans-regional water diversion project is the longest water supply line, measuring 263.5 km (163.7 mi), with the largest number of recipients benefiting from it in the history of Jilin Province. The construction project will divert the water from Fengman Reservoir at the upper reaches of Di’er Songhua River to central regions of Jilin Province experiencing chronic water shortages. These regions include the cities of Changchun and Siping, eight surrounding counties, and 26 villages and towns under their jurisdiction.  Tunneling is expected to be complete in late 2018.

Image 1: The 7.9 m (26 ft) Robbins Main Beam TBM achieved a national record for its size class, excavating 1,423.5 m (4,670 ft) in one month.
Image 2: The crew celebrates the national-record-setting Robbins TBM for China’s Jilin Lot 3 tunnel. The machine excavated in far more difficult ground at a higher rock strength than the current world record holder—also a Robbins TBM.
Image 3: The Robbins TBM was designed with pockets in the roof shield, allowing it to install the McNally Roof Support System while boring.

SippTech Awards $500K Contract for Sprayed in Place Pipe (SIPP) Technology Analysis to Louisiana Tech’s Trenchless Technology Center

Jacksonville, FL – SippTech LLC CEO/CTO Kent Weisenberg announced recently that the company has finalized a contract with Louisiana Tech’s Trenchless Technology Center for their continued partnership and product analysis of the advancement of Spray in Place Pipe Technology, (SIPP). The awarded contract specifically involves testing of SippTech’s robotic systems and installation of its cutting-edge, filament reinforced composite lining, SippSteel™.

“The Trenchless Technology Center (TTC) is excited to support SippTech through testing, research and developmental support of their innovative Spray-in-Place Pipe (SIPP) technology. This new SIPP technology has high potential to drive the pressure pipe rehabilitation industry forward in the very near future” stated Dr. John Matthews, Director of the TTC and Principal Investigator on the SippSteel™ project. Mr. Matthews further stated, “It is also a monumental moment for the TTC as this is the largest contract awarded to us from a private company since our conception.” Dr. Matthews will be assisted on this four-phased project by co- Principal Investigator’s Dr. Shaurav Alam and Dr. Amin Azimi. Industry professionals, undergraduate and graduate students will also be collaborating during each phase of testing.

SippSteel™ is comprised of a composite lining of two dissimilar lining material layers and a carbon fiber filament reinforcement, which are applied robotically in a single pass through the pipe system. The robotic apparatus is self-propelled, and all its mechanical functionalities are controlled autonomously by internal sensors and computer vision. Employing both individually specific and a synergetic combination of computer vision, LIDAR, ultrasound, RF, Wi-Fi, gyroscope, accelerometer and machine learning technologies, the robot can precisely navigate and apply the SippSteel™ composite inside of the pipe. The device can be operated via umbilical or autonomously providing lining lengths of more than a mile from one access point in the pipe.

“The SippSteel™ technology addresses a multitude of customer needs as well as resolving systemic problems in the trenchless technology sector. Today’s pipeline rehabilitation industry has long been searching for an innovative, and more importantly, versatile technology to fulfill all the structurally independent liner requirements” Mr. Weisenberg stated.

Innovative components that ensure that the SIPP system can deliver:

  • The ability to provide structurally independent rehabilitation; therefore, significantly optimizing the cost effectiveness and efficacy of the rehabilitation method as well as increasing the design life of the pipeline.
  • The ability to rehabilitate long lengths of pipe; therefore, substantially reducing installation time as well as costly and environmentally invasive excavations.
  • The ability to negotiate through pipe bends and valves; therefore, substantially reducing excavations that increase costs and disrupt the public.
  • The ability to provide a thinner liner system without a resulting annulus between the liner and the host pipe; thereby increasing the comparative cross-sectional diameter and subsequent flow capacity while impeding all potential for infiltration behind the liner which can result in hydraulic failure.

The Trenchless Technology Center (TTC) was initiated as the Trenchless Excavation Center in 1989 and formally established as the Trenchless Technology Center in November 1991. It was created to promote research, development and technology transfer in the trenchless technology industry.

“After several years of painstaking R&D we are tremendously enthusiastic to have entered the final analysis phase with such a highly credible institution as the TTC for the final verification of our compiled scientific testing and empirical data.” stated, Mr. Weisenberg. “We are proud to be revealing SippSteel™ and its capabilities which will revolutionize the  industry for the rehabilitation of pressure pipelines in an extensive range of diameters.” Mr. Weisenberg noted.

Please visit www.sipptech.com for more information on Spray in Place Pipe technology.

Contact:
Tiffany Laufer
SippTech Technologies, LLC.
tiffanyl@sipptech.com
904.374.5606