Robbins Double Shield Takes on Nepal’s First TBM Project for Bheri Babai

Irrigation and Hydroelectric Project to Ease Food Crisis in Mid-Western Region of Nepal

 Nepal will welcome its first TBM ever this summer, a 5.06 m (16.6 ft) diameter Double Shield machine for the Bheri Babai Diversion Multipurpose Project (BBDMP).  The Robbins TBM underwent its Factory Acceptance Testing in July 2017 and is currently being shipped to the jobsite in the Siwalik Range, part of the Southern Himalayan Mountains. Pre-construction, including laying gravel onto rural roads and excavating wells for drinking water, has been completed to make way for the TBM and its impending launch.

The BBDMP is one of Nepal’s 11 National Pride Projects–prioritized plans sanctioned by the Government of Nepal to further develop the mainly rural country. This project will irrigate 60,000 hectares (almost 15,000 acres) of land in the southern region of Nepal, benefitting an estimated 30,000 households. It will divert 40 cubic meters of water (1,400 cubic feet) per second from Bheri River to Babai River under a head of 150 m (492 ft) using a 15 m (49 ft) tall dam, providing year-round irrigation in the surrounding Banke and Bardia districts. The water will also be used for hydroelectricity, with a generating capacity of 48 MW benefiting the country with NPR 2 billion (20 million USD) annually.

Contractor China Overseas Engineering Group Co. Ltd. Nepal Branch (COVEC Nepal Branch), represented by China Railway No.2 Engineering Co., Ltd Chengtong Branch, is responsible for the headrace tunnel and is aware of the challenges associated with tunneling in tough geology. “The design of Robbins TBMs is good, and in particular Double Shield TBMs,” said Project Manager of BBDMP, Hu Tianran, for China Railway No.2 Engineering Co., Ltd Chengtong Branch. The Siwalik range is projected to consist of mainly sandstone, mudstone and conglomerate, requiring a TBM that can withstand squeezing ground, rock instability, possibly high ingress of water and fault zones. Maximum cover above the tunnel is 820 m (0.5 mi).

Due to the challenges in the young geology of the Himalayas, Difficult Ground Solutions (DGS) have been incorporated into the machine’s design. A stepped shield has been designed to move through squeezing ground. Robbins Project Engineer Missy Isaman talked about the DGS features incorporated into the TBM: “There is a probe drill in the rear that probes through the gripper shield in 14 places.  We added ports in the forward shield for drilling too. There are eight ports around the circumference for hand drilling.  There are also six ports in the top 100 degrees of the shield for forepoling.” She further noted that no equipment was ordered for either of the forward shield drilling options, but it’s easier to add the ports to the shield now, in case more comprehensive drilling is needed later in the bore. Other machine modifications included 35 mm (70 mm on the diameter) of possible overcut for gage cutters, and additional ports in the forward shield for dewatering.

Muck removal will be achieved by muck cars. Robbins will provide Field Service to support the machine erection, testing, commissioning and boring of the first 500 m (1,640 ft). The tunnel will be lined with hexagonal precast concrete segments.

The project owner, the Government of Nepal’s Ministry of Irrigation (MOI), has chosen a TBM over the traditional method of Drill &Blast due to the faster mobilization and rate of advance offered by mechanized mining. “The reason a TBM was chosen for this project was because using D&B method could have taken at least 12 years for project completion. This was due to there only being one excavation heading with no possibility of launching multiple operations using adit tunnels,” said Robbins General Manager for Nepal, Prajwal Man Shrestha. More generally, Mr. Shrestha saw the project as a way to prove that TBMs can indeed take on complex Himalayan rock. “Since the Himalayan range has a young geology and not much has been surveyed yet, the use of newer technology is looked upon with slight apprehension. The first few TBM projects and additional surveys will show how suitable TBM technology will be for the Himalayan Range.”

The success of the BBDMP, a national pride project, is paramount for the country as well as the TBM industry. It is expected to help aide the food crisis in the mid-western region of Nepal by increasing agricultural yields and invigorating socio-economic development in the region. The Robbins TBM for the 12.2 km (7.5 mi) tunnel is scheduled to launch in November 2017.

Image 1: The 5.06 m (16.6 ft) diameter Double Shield TBM will bore a 12.2 km tunnel from the Bheri River to Babai River.
Image 2: Due to the geological challenges in the Himalayas, DGS features have been added to the machine including a stepped shield, and dozens of ports throughout the front, rear and around the circumference of the machine.
Image 3:. Mr. Saroj Chandra Pandit, Deputy Director General of  DOI (Department of Irrigation) speaking at the Factory Acceptance Testing. Other speakers included Mr. Lin Qiang, Deputy Manager of China Railway No. 2 Engineering Co., Ltd and Mike Kolenich from Robbins.
Image 4: The Robbins crew, contractor COVEC Nepal Branch, and project officials stand proudly in front of the Robbins Double Shield TBM that will tackle the challenging geology in the Himalayas.

CCI Inc. Acquires Houston Based Horizontal Technology, Inc.

CALGARY, July 15, 2017 –CCI Inc., one of Canada’s Gold Standard Best Managed Companies http://ccisolutions.ca/ announces the acquisition of Houston based Horizontal Technology, Inc.

CCI Inc. is a leading expert in Horizontal Directional Drilling (HDD), Open-Cut and Micro-Tunneling methods. Since 2004, CCI has established itself as a driving force in the continued advancement of trenchless pipeline systems and employ proven methods for tackling difficult crossings.

With over 100 years of combined service in the HDD industry, Horizontal Technology, Inc. leads the way as the HDD industry’s premier guidance service and down-hole tooling provider.

For more information, please contact David Dupuis, COO, CCI. Inc. at ddupuis@ccisolutions.ca or 403-932-0560.

GSSI Announces New Engineering Focus on Developing Customized GPR Solutions for Variety of New Markets

GSSI, the world’s leading manufacturer of ground penetrating radar (GPR) equipment, announces a new engineering initiative focusing on using GPR to solve difficult problems that cannot be solved with any other technologies. Led by newly appointed Vice President of Research and Development David Cist, GSSI’s expert engineering team is focusing on new products for agriculture, manufacturing, robotic inspection, industrial quality assurance/quality control, power systems preventative maintenance, and unmanned autonomous vehicle applications. GSSI’s custom solutions create completely new products, different models of existing products, or a combination of the two.

“GSSI has a long established history of developing products based on custom needs, and has commercialized several that meet broader market needs,” said Cist. “The custom solutions engineering team brainstorms with customers who are looking for novel ways of handling problems. Often enough, GPR can offer a real solution to difficult problems that can’t be solved any other way. One recent outcome is the creation of a new GPR product line with a sensor that can be integrated into a variety of robots, drones, and other equipment.”

GSSI’s PaveScan® RDM asphalt density assessment tool, which provides accurate real-time measurements to ensure pavement life and quality, was originally developed based on work commissioned by the Texas Transportation Institute (TTI) as part of the Federal Highway Administration’s Strategic Highway Research Program (SHRP2). The commercial version is now being used by state departments of transportation in Minnesota, Alaska, Maine, and Florida, as well as globally in transportation research projects conducted by universities.

Other custom products commercialized by GSSI include the LifeLocator® TRx survivor detection system, which was originally developed in response to post-911 Homeland Security market needs. GSSI also developed one of the sensors used by the RABIT™ bridge deck assessment tool to determine bridge quality and bridge deterioration. RABIT™, developed by the Rutgers Center for Advanced Infrastructure and Transportation, is an autonomous robot that gathers quantitative data using several nondestructive evaluation technologies. The StructureScan Mini system was developed based on a specific request from one of GSSI’s largest customers in Japan, which years later was seeking a new software solution that would allow them to use the system to analyze insulated concrete forms.

The GSSI custom solution applications engineering team has developed GPR systems for golf course irrigation inspection, tree root inspection, horizontal drilling, detecting the porosity of bricks, and border patrol tunnel inspection systems. Applications under development include use of GPR to establish precise soil elevation and inspection of large and expensive equipment tires used in mining.

For more information on custom solutions and products based on GSSI’s GPR technology, contact sales@geophysical.com.

About GSSI

Geophysical Survey Systems, Inc. is the world leader in the development, manufacture, and sale of ground penetrating radar (GPR) equipment, primarily for the concrete inspection, utility mapping and locating, road and bridge deck evaluation, geophysics, and archaeology markets. Our equipment is used all over the world to explore the subsurface of the earth and to inspect infrastructure systems non-destructively. GSSI created the first commercial GPR system nearly 50 years ago and continues to provide the widest range and highest quality GPR equipment available today.

 

Straightline HDD Expands its Hole Opener Lineup

XL-I Series Hole Openers Are Designed From the Ground Up For HDD

(Hutchinson, Kansas) – StraightLine HDD recently expanded its hole opener offering with the introduction of the XL-I Series. Designed from the ground up for horizontal directional drilling, the XL-I Series is positioned as a cost-effective alternative to “split-bit” hole openers.

At the core of the design are proprietary cones—available in six sizes, in either Tungsten Carbide or Mill Tooth configurations. Mounted to a purpose-built platform, the design facilitates load transfer to the shaft and bearing, with minimal radial load. The result is a dramatic improvement in production, service life and consistency, bore after bore.

Next, designers set out to address wear and performance characteristics by re-examining the interplay between cone diameter, height and carbide placement. Cones are sized and attached to the baseplate at an angle that protects vulnerable surfaces. Shortened cone height further improves wear resistance. Carbides placed to cut independent paths yield higher efficiency and longer service life.

Internally, the cone’s proprietary sealing and bearing system mitigates fluid intrusion, yielding a myriad of user benefits, from reduced torque and fuel consumption to extended tool life.

As a platform, the XL-I Series incorporates design characteristics that ensure the tool’s original geometry is maintained—even after rebuild. This approach yields consistent and repeatable performance.

The XL-I Series includes six sizes, from 12.75- to 24-inches with IF Box x Box shafts.

About StraightLine HDD

Since 1984, StraightLine has produced drilling solutions” to the trenchless industry. It’s full line of down-hole tools, wear parts and accessories are known for their innovative and rugged design. The portfolio now includes the full array of hard condition tools under the Armadrillco brand. In 2015, StraightLine HDD merged operations with Source: HDD, Inc., a leading provider of used HDD rigs and support equipment. Together, the merger created a company offering total HDD solutions—from rig to bit. Call 620.802.0200 or visit www.straightlinehdd.com for details.

ISTT’s International No-Dig Awards Deadline Extended

Apply for ISTT’s International No-Dig Awards!

Deadline of submission: 15th August 2017 (Extended from 31st July!)
The winner will be announced at No-Dig Colombia  (25-27th September 2017)

Four categories are eligible to receive Awards as shown below. Awards may not be made in all categories in a given year.

  1. Academic research or training aid/course.
  2. Trenchless project completed.
  3. New machine, tool, material, system or technique introduced.
  4. Student or young professional paper – Members regularly enrolled in college or university, or spending at least half their time on academic course work

The aim of ISTT is to promote the science and practice of trenchless technology, and the Awards are to raise the profile and status of the Society and its Award Winners. All award winners (1) are recognized at the Gala dinner and presented a trophy and certificate, (2) are featured in an article in Trenchless International, (3) are added to the published list of ISTT award winner role of honor posted on the ISTT website, and (4) are authorized to use the ISTT logo on promotional material related to the award activity or recipients. In addition, the winner may be afforded an opportunity to make a brief presentation on the activity that received the award at the Conference time and schedule permitting. The student award winner receives a small cash award and limited financial travel assistance to attend the Conference. Visit the ISTT website for details!

Mexico City’s Record-Breaking Crossover TBM makes Final Breakthrough

Custom Robbins Machine finishes on a High Note under Low Cover

On June 8, 2017, a select group of project officials, including Mexico’s President Enrique Peña Nieto, celebrated the final breakthrough of an epic tunneling project.  The 8.7 m (28.5 ft) diameter Robbins Crossover TBM is the first such hybrid machine to operate in North America, and it completed the Túnel Emisor Poniente (TEP) II on a high note.  The TBM, known an XRE—a Crossover (X) between Rock (R) and EPB (E) TBMs—navigated fault zones, variable ground, low cover, and more to achieve a national record of 57 m (187 ft) in one day as well as maximum rates of 231 m (758 ft) in one week and 702 m (2,303 ft) in one month.

“The XRE has a great advantage as it is designed to work in open and/or closed mode (EPB); allowing it to excavate the tunnel either in soil or in rock. We’ve verified that its performance was very efficient,” said Ing. Juan Alberto Herrera Moro y Castillo, TEP II Section Chief for owner CONAGUA, Mexico’s National Water Commission.

The unique machine and its Robbins continuous conveyor system were built on location using Onsite First Time Assembly (OFTA), and designed for a contractor consortium of Aldesem, Proacon, and Recsa. The Robbins XRE TBM featured components like a convertible cutterhead with interchangeable cutting tools, interchangeable TBM belt conveyor and screw conveyor, and multi-speed gearboxes to increase torque for tunneling through difficult ground. “The benefits of the design are in its exceptional thrust power and in the ease of changing the cutterhead torque. This makes the process much easier should the machine become stuck in difficult ground,” said Alberto Martinez, head of the tunneling department for RECSA.

The XRE machine was launched in August 2015 to bore the 5.8 km (3.6 mi) long wastewater tunnel.  The machine was set up in a hard rock configuration and mounted with 20-inch diameter disc cutters. Early in 2016 the TBM hit the first of several contact zones, a 30 m (98.4 ft) wide fault of fractured and blocky rock. While the excavation through the contact zone was slow going, progress picked up again in the more competent andesite rock. After an intermediate breakthrough in March 2016 into an 80 m (262.5 ft) deep shaft followed by inspection and maintenance, the TBM continued on.

While boring in fractured andesite rock in autumn 2016, the TBM encountered a naturally occurring cavern believed to be the result of either a rock fall in a transition zone, or an old, underground lake body that had eroded the rock away.  The cavern was estimated at 90 cubic meters (3,200 cubic ft) in size, including about 57 cubic meters (2,010 cubic ft) of unstable floor area. The TBM was stopped and immediate measures were taken to stabilize the ground in front of the machine with polyurethane foam before filling the cavern with a mixture of pea gravel and grout.

By the end of October 2016, the TBM had reached a final 900 m (2,950 ft) long section of soft ground, where it was converted to EPB mode. In this final reach of tunnel with low cover, the distance from the top of the tunnel to residential home foundations was as low as 4 m (13 ft), and the ground had the consistency of reconsolidated soil.  In order to stabilize the soft soils and minimize the risk of settlement below the residential area, the tunneling crew drilled from the surface and installed 890 micro-piles at 1.0 m (3.3 ft) intervals.  “We were able to do this without causing damage to property owned by neighbors in the zone bordering the path of TEP II, or to the road or the urban infrastructure installed in that area,” explained Ing. Francisco Miguel Lopez, Jobsite Manager TEP II for contractor Aldesa.

Now that tunneling is complete, the tunnel will receive a secondary concrete lining of 35 cm (14 in) thickness before going into service. The wastewater tunnel will overhaul the current system in western areas outside of Mexico City and serve to prevent recurrent flooding in Valle Dorado. In particular, the tunnel will benefit the cities of Cuautital Izcalli, Tlalnepantla, and Atizapan de Zaragoza, which altogether are home to 2.1 million inhabitants.

Image 1: The 8.7 m (28.5 ft) diameter Robbins XRE TBM was the first Crossover machine to bore in North America.
Image 2: Robbins personnel stand proudly in front of the Crossover TBM for Túnel Emisor Poniente (TEP) II—the project resulted in challenges as well as national records for TBM advance.
Image 3: During its bore, the Crossover achieved a national record for TBM advance, excavating 57 m (187 ft) in one day as well as achieving high rates of 231 m (758 ft) in one week and 702.2 m (2,303 ft) in one month.